The event and the effect are separate

War, mines, blockade, government orders, and obstruction may appear on a force-majeure list. That establishes only a possible event. The invoking party must still show the contractual effect on a specific obligation, plus any required control, foreseeability, avoidance, notice, and mitigation elements.

Regional conflict is not self-executing relief.

English law starts with the contract

Force majeure is not a free-standing English-law doctrine that excuses performance whenever extraordinary events occur. Rights come from the clause the parties agreed, interpreted with the rest of the charter.

BIMCO's explanatory notes make this contractual foundation explicit and warn against casual incorporation.

Use the signed wording, not a checklist

Some clauses require prevention; others include hindrance or delay. Some list war but exclude foreseeable events. Some demand notice within hours; others say without delay. Remedies can suspend liability, extend time, allocate cost, or permit termination.

Small drafting differences can reverse the commercial result.

BIMCO uses a structured threshold

Its Force Majeure Clause 2022 requires a defined event beyond reasonable control that could not reasonably have been foreseen, avoided, or overcome, and that prevents contractual performance. The party invoking it must prove the conditions.

Higher cost, reduced profitability, or increased danger alone may not satisfy prevention.

War is on the list

BIMCO lists actual, threatened, or reported war, hostilities, mines, piracy, terrorism, blockade, governmental action, obstruction of waterways, and certain system failures among possible events.

Being listed does not remove the remaining causal and procedural tests or any negligence carve-out that applies.

Foreseeability is difficult in 2026 fixtures

For contracts concluded after Gulf hostilities and Hormuz disruption became public, a party may struggle to say the general risk was unforeseeable under wording like BIMCO's. The precise later development could still be distinct.

Fixture files should show what parties knew and what risks they priced or allocated expressly.

Alternative performance can defeat prevention

If charterers can nominate another safe port, employ the vessel elsewhere, use another route, or arrange lawful cargo handling, performance may be avoidable rather than prevented. BIMCO specifically warns about broad-trading time charters because alternative employment may resolve the event.

Operational inconvenience does not necessarily equal impossibility.

Cargo aboard narrows the options

Once laden, the carrier must protect and deliver goods under carriage documents. BIMCO offers optional cargo-on-board machinery involving a waiting period, proposed alternatives, and safe discharge when no response arrives.

Those optional provisions apply only if incorporated and completed appropriately; they are not implied into every charter.

Notice is a substantive control

The BIMCO clause requires written notice without delay identifying the event and anticipated effect. Relief from breach begins from valid notice under its wording. A vague email saying “force majeure” may not explain which duty is prevented or why.

State facts, obligations, effect, start time, expected duration, and mitigation.

Notice must be updated

The affected party must provide relevant information and notify when prevention ceases. Gulf conditions can change rapidly as routes, ports, insurance, and official directions reopen.

A valid first notice does not justify silence after an alternative becomes workable.

Mitigation is active performance

Reasonable endeavors can include alternative orders, ports, routes, cargo arrangements, insurers, permits, suppliers, or schedules. The required steps depend on cost, safety, legality, urgency, and contract.

Keep rejected alternatives and reasons, not just a statement that none existed.

Cooperation does not erase rights

BIMCO directs parties to cooperate and discuss alternative performance in good faith. They can do so under reservation, without conceding liability or waiving accrued payment.

Structured operational calls should produce action lists while formal notices preserve each party's contractual position.

Payment duties usually continue

The BIMCO form states that payment obligations remain unless directly affected. Accrued hire, freight, demurrage, premium reimbursement, or undisputed invoices do not vanish merely because another operational duty is prevented.

Identify each payment and its causal link instead of suspending all cash flows.

War clauses are more specific

CONWARTIME and VOYWAR provide detailed mechanisms for refusal, alternative orders, rerouting, discharge, insurance costs, hire, and freight. BIMCO's 2026 Gulf guidance says clauses must be read together and no provision operates in isolation.

A general force-majeure clause should not bypass a specific risk allocation without careful interpretation.

Off-hire and laytime remain separate

Force majeure relief from damages does not necessarily stop hire, laytime, or demurrage. BIMCO's optional charter wording says these clocks remain governed by applicable charter provisions.

Parties must analyze performance relief and time-payment machinery on separate tracks.

Termination is a high threshold

The BIMCO form permits termination for performance that becomes impossible, illegal, or radically different, or after an agreed long-stop where substantial effect continues. The second route does not operate if parties leave the days blank.

Termination concerns future obligations and does not automatically erase accrued rights.

Hypothetical COA shipment

Assume a contract of affreightment requires monthly Gulf liftings. Hormuz is dangerous, but one shipment can move through a safe alternate load range while another cannot. The clause lists war and requires prevention.

This is hypothetical. Relief may apply shipment by shipment rather than cancel the entire COA, depending on text and causation.

Evidence must prove the causal chain

Preserve official orders, port status, mine warnings, insurer requirements, vessel position, cargo state, alternative quotations, nominations, banking restrictions, permits, and communications. Show how the event prevented the identified obligation during the claimed period.

Market reports about general disruption are context, not proof of this contract's prevention.

Forecast: Gulf clauses will narrow generic relief

Parties are likely to supplement force majeure with detailed Hormuz provisions on safe waiting, alternative employment, trapped vessels, insurance, time, and termination. This is a forecast, not an adopted industry rule.

Specific drafting can improve certainty but may deliberately remove relief that a broad clause appeared to offer.

A force-majeure proof table

Record clause, event, obligation, prevention or delay test, control, foreseeability, avoidance, start, notice, information supplied, mitigation, alternative performance, cooperation, payment effects, hire or laytime, cargo status, long-stop, cessation, termination, and reservations.

Test each obligation separately rather than declaring the whole charter “in force majeure.”

The ZeaClub view

Force majeure is a causal mechanism, not a geopolitical description. The Gulf can be at war while a charter duty remains possible, and one duty can be prevented while payment and cargo-care duties continue.

Commercially disciplined parties name the event, identify the exact obligation, prove prevention, notify promptly, test alternatives, and keep time clauses separate. The phrase should begin an analysis, never end it.

This article distinguishes verified source material from ZeaClub analysis, recommendations, forecasts and hypothetical scenarios.

Sources